Emmvee Photovoltaic Power Ltd: management guidance tracker
What management said it would deliver, when, where they said it — and what the reported numbers showed afterwards.
How to read this page — 30 seconds
- Latest guidance is what management said at its most recent results call, presentation or interview, next to what it had said before. Raised or Lowered tells you which way expectations moved.
- Other open guidance lists earlier promises that have not fallen due, soonest first, with the latest reported figure.
- Track record compares each promise that has fallen due with what the company actually delivered. That is the best guide to how much weight to give the new guidance.
Select any row for management's exact words, where they said it and how the target changed over time.
Latest guidance · 14 Oct 2026 – 21 Oct 2026
From Concall transcript — Q2FY27 (21 Oct 2026), Investor presentation — Q2FY27 (14 Oct 2026). What management guided for most recently, against what it had said before.
EBITDA for the whole FY27
Direct
FY27 EBITDA guidance of around INR2,400 crore reaffirmed, with management saying H1 numbers make it comfortable to reach.
Earlier
First time stated
Now~₹2,400 CrFY27
Change
New
StatusBehind
So far: ₹1,105 Cr
In management's words
“previously, you have guided around INR2,400 crores of EBITDA for the whole FY27. Do we still stand by that guidance or is there any update on that?”
What it implies in numbers
Reaching ₹2,400 Cr by FY27 from ₹1,734 Cr (FY26) needs about 38.4% growth a year.
How it was checked
₹1,105 Cr booked in Q1FY27–Q2FY27 — 46% of the ₹2,400 Cr guided for FY27 with 50% of the period gone (simple pro-rata, ignores seasonality).
How this guidance changed
Stated once in the documents read so far.
Effective cell capacity utilisation · cell
Direct
Walked back
Cell utilisation expected to stay close to 90% for the remaining two quarters of FY27.
Earlier
85–90%by FY26 · 2 Dec 2025
Now~90%by FY27
Change
Deadline pushed out
StatusPending
In management's words
“we should continue to see these utilization rates, which is close to 90% for the remaining remaining two quarters.”
How it was checked
Capacity utilisation is not in the stored financial tables.
How this guidance changed
- 2 Dec 2025 — 85–90% for by FY26
First stated
Concall transcript · Partly achieved (actual About 85% in March 2026 exit, but 79% for Q4 FY26 and 69.9% for full FY26)
- 21 Oct 2026 — ~90% for by FY27
Deadline pushed out
Concall transcript · Pending
Modules capacity, ongoing projects · Solar modules
Direct
Walked back
Module capacity is shown reaching 16.3 GW by FY27, conflicting with the early FY28 date given on page 9.
Earlier
16.3 GWby FY28 · 2 Sep 2026
Now16.3 GWby FY27
Change
Deadline brought forward
StatusPending
In management's words
“16.3 GW by FY27”
How it was checked
Capacity is not in the stored financial tables.
How this guidance changed
- 15 Jul 2026 — ~16.3 GW for by H1FY28
First stated
Press release · On track (actual 10.3 GW installed module capacity in FY26)
- 2 Sep 2026 — 16.3 GW for by FY28
Deadline pushed out
Annual report · On track
- 14 Oct 2026 — 16.3 GW for by FY27
Deadline brought forward
Investor presentation · Pending
TOPCon cell capacity · Solar cells
Direct
TOPCon cell capacity is to reach 8.94 GW by H1 FY28 after the expansion.
Earlier
8.94 GWH1FY28 · 28 Apr 2026
Now8.94 GWH1FY28
Change
Repeated
StatusPending
In management's words
“TOPCon Cell Capacity To Reach 8.94 GW By H1 FY'28 (Post Expansion)”
How it was checked
Capacity is not in the stored financial tables.
Condition attached by management: Post expansion
How this guidance changed
- 15 Jan 2026 — 8.94 GW for H1FY28
First stated
Concall presentation · On track (actual Installed TOPCon cell capacity of 2.94 GW as of Q1 FY27, with the 6 GW integrated expansion reported in line with plan)
- 28 Apr 2026 — 8.94 GW for H1FY28
Repeated
Concall presentation · On track
- 14 Oct 2026 — 8.94 GW for H1FY28
Repeated
Investor presentation · Pending
Total capacity · Solar PV modules
Direct
Module capacity is to rise to about 16.3 GW by early FY28 through the 6 GW integrated expansion.
Earlier
16.3 GWby FY28 · 28 Apr 2026
Now~16.3 GWby FY28
Change
Repeated
StatusPending
In management's words
“which will increase total capacity to approximately 16.3 GW of modules and 8.9 GW of cells by early FY28”
How it was checked
Capacity is not in the stored financial tables.
How this guidance changed
- 28 Apr 2026 — 16.3 GW for by FY28
First stated
Concall presentation · On track (actual Installed module capacity of 10.3 GW as of Q1 FY27 against a 16.3 GW FY28 target)
- 14 Oct 2026 — ~16.3 GW for by FY28
Repeated
Investor presentation · Pending
Total capacity · Solar cells
Direct
Walked back
Cell capacity is to rise to about 8.9 GW by early FY28 through the 6 GW integrated expansion.
Earlier
8.94 GWby FY28 · 2 Sep 2026
Now~8.9 GWby FY28
Change
Repeated
StatusPending
In management's words
“which will increase total capacity to approximately 16.3 GW of modules and 8.9 GW of cells by early FY28”
How it was checked
Capacity is not in the stored financial tables.
How this guidance changed
- 28 Apr 2026 — 8.9 GW for by FY28
First stated
Concall presentation · On track
- 15 Jul 2026 — ~8.9 GW for by H1FY28
Deadline brought forward
Press release · On track
- 2 Sep 2026 — 8.94 GW for by FY28
Deadline pushed out
Annual report · On track
- 14 Oct 2026 — ~8.9 GW for by FY28
Repeated
Investor presentation · Pending
Rollout phase 1 · Ingot and wafer backward integration
Direct
The first phase of the 9 GW ingot and wafer facility is planned as 5 GW in FY29.
Earlier
First time stated
Now5 GWFY29
Change
New
StatusPending
In management's words
“Rollout to be in 2 phases: 5 GW in FY29 and 4 GW in FY30”
How it was checked
Capacity is not in the stored financial tables.
Condition attached by management: Subject to final clarity on ALMM III timelines and market conditions
How this guidance changed
Stated once in the documents read so far.
Rollout phase 2 · Ingot and wafer backward integration
Direct
The second phase of the 9 GW ingot and wafer facility is planned as 4 GW in FY30.
Earlier
First time stated
Now4 GWFY30
Change
New
StatusPending
In management's words
“Rollout to be in 2 phases: 5 GW in FY29 and 4 GW in FY30”
How it was checked
Capacity is not in the stored financial tables.
Condition attached by management: Subject to final clarity on ALMM III timelines and market conditions
How this guidance changed
Stated once in the documents read so far.
Capex for 6 GW integrated cell and module project · cell and module
Direct
Total cost of the 6 GW cell and module expansion is about INR5,500 crore, including about INR4,600 crore hard cost.
Earlier
First time stated
Now₹5,500 CrNot specified
Change
New
StatusPending
In management's words
“that INR5,500 crores are for both cell and module of 6 gigawatt each. And it includes, where the hard cost is around INR4,600 crores”
How it was checked
Segment-level guidance cannot be read from company-level numbers.
Condition attached by management: includes IDC, contingency and working capital margin, not only hard cost
How this guidance changed
Stated once in the documents read so far.
Debt for the project
Direct
Debt of about Rs 3,300 crore is expected to part-fund the expansion project.
Earlier
First time stated
Now~₹3,300 CrNot specified
Change
New
StatusPending
In management's words
“Debt of approximately ₹3,300 crore.”
How it was checked
No timeline was given; tracked against each new result.
How this guidance changed
Stated once in the documents read so far.
Estimated capex
Direct
Estimated capex for the expansion and backward integration is Rs 5,000-5,500 crore, largely funded from internal accruals.
Earlier
₹4,500 Cr – ₹4,800 CrNot specified · 2 Sep 2026
Now₹5,000 Cr – ₹5,500 CrNot specified
Change
Raised
StatusPending
In management's words
“Estimated capex is ₹5,000-5,500 crore, broadly implying ₹600-650 crore per GW. To be funded largely through internal accruals”
How it was checked
No timeline was given; tracked against each new result.
Condition attached by management: Funded largely through internal accruals
How this guidance changed
- 2 Sep 2026 — ₹4,500 Cr – ₹4,800 Cr for Not specified
First stated
Annual report · Pending
- 14 Oct 2026 — ₹5,000 Cr – ₹5,500 Cr for Not specified
Raised
Investor presentation · Pending
Module capacity utilisation range · module
Direct
Module utilisation expected broadly in the 45% to 60% range going forward.
Earlier
First time stated
Now45–60%Not specified
Change
New
StatusPending
In management's words
“So, with that, keeping in mind, our utilizations will be broadly in the range of 45% to 60%.”
How it was checked
Capacity utilisation is not in the stored financial tables.
Condition attached by management: flexibility to choose markets opportunistically
How this guidance changed
Stated once in the documents read so far.
Total installed cell manufacturing capacity upon completion · cell
Direct
Total installed cell manufacturing capacity to rise to about 8.9 GW on completion of the expansion.
Earlier
8.9 GWby H2FY27 · 29 Apr 2026
Now~8.9 GW of cellsNot specified
Change
Repeated
StatusPending
In management's words
“Upon completion, our total installed manufacturing capacity will increase to approximately 16.3 gigawatt of modules and 8.9 gigawatt of cells.”
How it was checked
Capacity is not in the stored financial tables.
Condition attached by management: upon completion of the expansion
How this guidance changed
- 29 Apr 2026 — 8.9 GW for by H2FY27
First stated
Concall transcript · On track
- 21 Oct 2026 — ~8.9 GW of cells for Not specified
Repeated
Concall transcript · Pending
Total installed manufacturing capacity upon completion · module
Direct
Total installed module manufacturing capacity to rise to about 16.3 GW on completion of the expansion.
Earlier
16.3 GWby H2FY27 · 29 Apr 2026
Now~16.3 GW of modulesNot specified
Change
Repeated
StatusPending
In management's words
“Upon completion, our total installed manufacturing capacity will increase to approximately 16.3 gigawatt of modules and 8.9 gigawatt of cells.”
How it was checked
Capacity is not in the stored financial tables.
Condition attached by management: upon completion of the expansion
How this guidance changed
- 29 Apr 2026 — 16.3 GW for by H2FY27
First stated
Concall transcript · On track (actual 10.3 GW installed module capacity in FY26)
- 21 Oct 2026 — ~16.3 GW of modules for Not specified
Repeated
Concall transcript · Pending
Module line commissioning · Solar modules
Indirect
The module line is expected to be commissioned by December 2026.
Earlier
milestoneby Dec 2026 · 15 Jul 2026
Nowmilestoneby Dec 2026
Change
Repeated
StatusPending
In management's words
“Module line is expected to be commissioned by December 2026”
How it was checked
Milestone guidance is checked against later documents.
Condition attached by management: Commercial sales to be aligned with commissioning dates
How this guidance changed
- 15 Jul 2026 — milestone for by Dec 2026
First stated
Press release · On track
- 14 Oct 2026 — milestone for by Dec 2026
Repeated
Investor presentation · Pending
Cell line commissioning · Solar cells
Indirect
The cell line is expected to be commissioned by March 2027.
Earlier
milestoneby Mar 2027 · 15 Jul 2026
Nowmilestoneby Mar 2027
Change
Repeated
StatusPending
In management's words
“with the cell line expected by March 2027”
How it was checked
Milestone guidance is checked against later documents.
Condition attached by management: Commercial sales to be aligned with commissioning dates
How this guidance changed
- 15 Jul 2026 — milestone for by Mar 2027
First stated
Press release · On track
- 14 Oct 2026 — milestone for by Mar 2027
Repeated
Investor presentation · Pending
Order book to be delivered
Indirect
About 5 to 5.5 GW of the 10.4 GW order book expected to be delivered in the next 12 to 15 months.
Earlier
First time stated
Now5–5.5 GWFY27–FY28
Change
New
StatusPending
In management's words
“Out of the 10.4 gigawatts order book, we should have about 5 gigawatts that is delivered, 5 gigawatts to 5.5 GW that is delivered in the next 12 to 15 months.”
How it was checked
Order book is not in the stored financial tables.
Assumptions made in reading this
- horizon counted from FY26 (last completed year at the statement date)
How this guidance changed
Stated once in the documents read so far.
Finance cost during the capitalisation period
Hint
Finance cost expected to stay at similar levels until December, as interest is capitalised until the module line is commissioned.
Earlier
First time stated
Nowto hold or improveby Q3FY27
Change
New
StatusPending
In management's words
“This will be till December. Once the module line is commissioned, a portion of the interest will be recognized in March quarter”
Condition attached by management: interest capitalised until commissioning
How this guidance changed
Stated once in the documents read so far.
Module manufacturing facility commissioning · module
Hint
Module manufacturing facility of the 6 GW expansion to be commissioned by December 2026.
Earlier
First time stated
Nowmilestoneby Q3FY27
Change
New
StatusPending
In management's words
“We expect the commissioning of the module manufacturing facility by December, followed by cell manufacturing facility by March 2027.”
How it was checked
Milestone guidance is checked against later documents.
How this guidance changed
Stated once in the documents read so far.
Quarterly order inflow
Hint
Management expects order inflows to continue rising quarter on quarter as the 6 GW expansion approaches.
Earlier
First time stated
Nowto improveQ3FY27
Change
New
StatusPending
In management's words
“Sir, certainly, you are continuing to see a quarterly uptick.”
How it was checked
Order inflow is not in the stored financial tables.
How this guidance changed
Stated once in the documents read so far.
Capacity utilisation
Hint
Utilisation of the new lines is expected to scale steadily as commercial sales follow commissioning.
Earlier
to improveFY27 · 2 Sep 2026
Nowto improveFY27
Change
Repeated
StatusOn track
So far: 89% cell utilisation in Q2FY27, described as a strong ramp
In management's words
“Commercial Sales to be aligned with the commissioning dates, with utilisations scaling steadily”
How it was checked
Deadline is FY27, not yet passed. Management describes a strong ramp with 89% cell utilisation, but no new-line trajectory is given and module utilisation is only 44%. (judged from later company statements)
Evidence (21 Oct 2026): “achieving 89% effective capacity utilization during the quarter.” — Concall transcript — Q2FY27 (21 Oct 2026)
Evidence (21 Oct 2026): “Module capacity utilization stood at approximately 44%.” — Concall transcript — Q2FY27 (21 Oct 2026)
Condition attached by management: Commercial sales aligned with commissioning dates
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
- 2 Sep 2026 — to improve for FY27
First stated
Annual report · Pending
- 14 Oct 2026 — to improve for FY27
Repeated
Investor presentation · On track (actual 89% cell utilisation in Q2FY27, described as a strong ramp)
Cell manufacturing facility commissioning · cell
Hint
Cell manufacturing facility of the 6 GW expansion to be commissioned by March 2027.
Earlier
First time stated
Nowmilestoneby Mar 2027
Change
New
StatusPending
In management's words
“We expect the commissioning of the module manufacturing facility by December, followed by cell manufacturing facility by March 2027.”
How it was checked
Milestone guidance is checked against later documents.
How this guidance changed
Stated once in the documents read so far.
Recognition of full interest cost in P&L
Hint
Full interest cost to be recognised in the P&L from the first quarter of next year, after capitalisation ends.
Earlier
First time stated
Nowto improveQ1FY28
Change
New
StatusPending
In management's words
“a portion of the interest will be recognized in March quarter and full amount will begin to be recognized from first quarter of next year.”
Condition attached by management: after commissioning of the module and cell lines
How this guidance changed
Stated once in the documents read so far.
Margin per watt (module pricing and margin) · module
Hint
Management expects margin to be maintained even though module prices may fall, as efficiency gains are passed to customers.
Earlier
First time stated
Nowto hold or improveFY28
Change
New
StatusPending
In management's words
“With the value addition and other things, definitely the prices will going to be little less, but margin can be maintained.”
How it was checked
Gross margin is not in the stored financial tables.
Condition attached by management: value addition and manufacturing efficiency gains
How this guidance changed
Stated once in the documents read so far.
Other open guidance · soonest due first
Earlier promises that have not fallen due yet, with the latest figure where one has been reported.
Order book growth
Hint
Order book is expected to grow only in line with capacity growth, maintaining a 12-18 month delivery period.
Targetto improve
DueFY26
result by 30 May 2026
Said2 Dec 2025
Concall transcript
StatusAwaiting data
In management's words
“we are only growing to the extent of our capacity growth and we are not taking multiple times of capacity.”
How it was checked
Order book is not in the stored financial tables.
Assumptions made in reading this
- no time frame was stated; checked on FY26, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
6 GW greenfield cell expansion at ITIR Phase 2 · cell
Indirect
The 6 GW greenfield cell expansion is expected to be fully operational and ramped up by end of March 2027, or possibly April 2027.
Targetmilestone
Dueby Mar 2027
result by 30 May 2027
Said2 Dec 2025
Concall transcript
StatusOn track
In management's words
“that we expect to become on a fully operational basis, on a ramped up basis by end of March 2027. Kind of March 2027 or April 2027.”
How it was checked
The deadline of March 2027 has not passed, and the 6 GW integrated expansion is reported in line with plan, though the evidence does not name this specific greenfield phase. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (15 Jul 2026): “our on-track 6 GW integrated expansion give us confidence as we enter the next phase of India’s solar manufacturing growth.” — Press release — Q1FY27 (15 Jul 2026)
How this guidance changed
Stated once in the documents read so far.
Silver paste consumption
Direct
Management sees an opportunity to cut silver paste consumption by a further 40% from current levels, with no timeline given.
Target~40% growth
DueFY27
result by 30 May 2027
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“the targeted consumption of silver paste, there is an opportunity to bring it down another 40%”
How it was checked
Other is not in the stored financial tables.
Condition attached by management: Further from current consumption, not from the base; depends on process and technology R&D.
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
EBITDA per watt peak
Hint
Management expects EBITDA per watt peak to stay at current levels for both DCR and non-DCR products going forward.
Targetto hold or improve
DueFY27
result by 30 May 2027
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“We don't see any pressure in that EBITDA per watt even going forward.”
Condition attached by management: Assumes contracts remain pass-through for material cost changes.
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
Captive versus third-party cell use · cells
Hint
Management expects most cell capacity to serve captive module production, with limited third-party cell sales.
Targetto hold or improve
DueFY27
result by 30 May 2027
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“Most of our capacity will be used for captive consumption, third party catering will be limited.”
How it was checked
Capacity is not in the stored financial tables.
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
Utility scale DCR demand · utility scale
Hint
Management expects utility-scale DCR demand to start in about 9 to 12 months, after C&I DCR demand has already begun.
Targetmilestone
DueFY27–FY27
result by 30 May 2027
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“utility scale will take still about another 9 to 12 months”
How it was checked
Milestone guidance is checked against later documents.
Assumptions made in reading this
- horizon counted from FY26 (statement made in its last quarter)
How this guidance changed
Stated once in the documents read so far.
Standalone solar cell sales · cells
Hint
Management expects a standalone solar cell market to persist only to a very small extent, not as a majority of demand.
Targetto come down
DueFY27
result by 30 May 2027
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“No, I think that that will exist to a very small extent but that will not be a majority that will be a very small portion.”
How it was checked
Segment-level guidance cannot be read from company-level numbers.
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
Capacity addition for next phase of growth
Hint
Management says it is building foundations for the next phase of growth through further capacity additions.
Targetto improve
DueFY27
result by 30 May 2027
Said16 Jan 2026
Concall transcript
StatusOn track
In management's words
“we continue to build the foundations for the next phase of growth with capacity addition and progress in integration.”
How it was checked
The FY27 deadline has not passed, and later reports describe capacity additions as on plan, though the statement is qualitative. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (15 Jul 2026): “our on-track 6 GW integrated expansion give us confidence as we enter the next phase of India’s solar manufacturing growth.” — Press release — Q1FY27 (15 Jul 2026)
Evidence (29 Apr 2026): “With this, our module capacity expansion for the year was completed as planned.” — Concall transcript — Q4FY26 (May 2026)
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
PAT margin
Hint
Management expects the improved PAT margin to be sustained, supported by EBITDA strength and lower finance costs.
Targetto hold or improve
DueFY27
result by 30 May 2027
Said28 Apr 2026
Concall presentation
StatusPending
In management's words
“PAT margin expansion to sustain due to strength in EBITDA and lower finance costs”
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
Unit 7 commissioning window · Solar modules and cells
Indirect
Unit 7, a 6 GW module and cell facility, is shown with a commissioning window of 2026-2027.
Targetmilestone
Dueby FY27
result by 30 May 2027
Said28 Apr 2026
Concall presentation
StatusOn track
In management's words
“Integrated Capacity Expansion Unit 7 2026-2027”
How it was checked
Later statements report the 6 GW expansion progressing in line with plan. Commissioning of the unit within the 2026-2027 window is not yet confirmed, and the FY27 deadline has not passed. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (2 Sep 2026): “We commissioned two 2.5 GW solar module manufacturing lines at Sulibele, taking total module installed capacity to 10.3 GW” — Annual report FY26
Evidence (15 Jul 2026): “our on-track 6 GW integrated expansion give us confidence as we enter the next phase of India’s solar manufacturing growth.” — Press release — Q1FY27 (15 Jul 2026)
How this guidance changed
Stated once in the documents read so far.
EBITDA spread / margins going into FY27
Hint
Margins going into FY27 are expected to be similar to FY26 levels, including on new orders.
Targetto hold or improve
DueFY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript · 2× since 16 Jan 2026
StatusPending
In management's words
“whatever, like, you know, the margins that we are seeing going into FY27 is not very different to what we have seen earlier.”
How this guidance changed
- 16 Jan 2026 — to hold or improve for FY27
First stated
Concall transcript · Pending
- 29 Apr 2026 — to hold or improve for FY27
Repeated
Concall transcript · Pending
Module line commissioning (6 GW integrated facility) · module
Hint
Module line of the 6 GW integrated facility at Devanahalli is expected to be commissioned by end of calendar 2026.
Targetmilestone
Dueby H2FY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusOn track
In management's words
“we expect to see the module line getting commissioned by the end of this calendar year”
How it was checked
Management says the facility is in line with plan, but no evidence yet shows the module line commissioned. The calendar-2026 deadline has not passed as of 19 Nov 2026. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (15 Jul 2026): “our on-track 6 GW integrated expansion give us confidence as we enter the next phase of India’s solar manufacturing growth.” — Press release — Q1FY27 (15 Jul 2026)
Evidence (21 Oct 2026): “Module capacity utilization stood at approximately 44%.” — Concall transcript — Q2FY27 (21 Oct 2026)
Evidence (21 Oct 2026): “solar module production increased by approximately 40% year-on-year to 952 megawatts” — Concall transcript — Q2FY27 (21 Oct 2026)
How this guidance changed
Stated once in the documents read so far.
Cell line commissioning (6 GW integrated facility) · cell
Hint
Cell line of the 6 GW integrated facility is expected to be commissioned at the end of FY27.
Targetmilestone
Dueby Q4FY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusOn track
In management's words
“the cell line getting commissioned at the end of this financial year.”
How it was checked
Later statements say the 6 GW integrated expansion is in line with plan. Cell line commissioning has not yet been reported, and the end-FY27 deadline has not passed. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (2 Sep 2026): “We commissioned two 2.5 GW solar module manufacturing lines at Sulibele, taking total module installed capacity to 10.3 GW” — Annual report FY26
Evidence (15 Jul 2026): “our on-track 6 GW integrated expansion give us confidence as we enter the next phase of India’s solar manufacturing growth.” — Press release — Q1FY27 (15 Jul 2026)
Evidence (21 Oct 2026): “achieving 89% effective capacity utilization during the quarter.” — Concall transcript — Q2FY27 (21 Oct 2026)
How this guidance changed
Stated once in the documents read so far.
IREDA term loan drawdown by 31 March
Direct
About 75-80% of the INR3,306 crore IREDA loan is expected to be drawn by 31 March 2027, with 15-20% spilling into FY28.
Target75–80%
Dueby Q4FY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusPending
In management's words
“So, by 31st March, probably around 75% to 80% will be drawing, and rest possibly because we will have some retention payment also, which is 15% to 20%, that will be spilling over to FY28.”
How it was checked
Other is not in the stored financial tables.
Condition attached by management: Drawdown timed to optimise interest cost
How this guidance changed
Stated once in the documents read so far.
Ingot and wafer Phase 2 expansion · ingot-wafer
Indirect
Ingot and wafer Phase 2 is planned at 4 GW, about a year after Phase 1.
Target4 GW
Dueby FY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusBehind
In management's words
“So, with the expansion, we’re looking at a 5 gigawatt expansion in Phase 1 and a 4 gigawatt expansion in Phase 2, which is going to be a year after.”
How it was checked
Phase 1 is now expected to start in FY2028-29, which places the 4 GW Phase 2 after the FY27 deadline. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Assumptions made in reading this
- horizon counted from FY26 (last completed year at the statement date)
How this guidance changed
Stated once in the documents read so far.
Utilisation of existing capacity
Hint
Management will continue ramping utilisation across existing capacity.
Targetto improve
Dueby Q4FY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusOn track
So far: Cell utilisation rose to 89% in Q2FY27, from 83% in Q1FY27 and 70% in FY26; module utilisation was 44%
In management's words
“we will continue ramping up utilization across our existing capacity”
How it was checked
Cell utilisation has ramped from 70% to 89%, but module utilisation slipped from 45% to 44%. The Q4FY27 deadline has not passed, so ramping is mixed but ongoing. (judged from later company statements)
Evidence (2 Sep 2026): “Cell capacity utilisation improved to approximately 70%, demonstrating successful ramp-up of integrated manufacturing operations.” — Annual report FY26
Evidence (15 Jul 2026): “Effective solar cell capacity utilisation improved to a record 83%, from 68% in Q1 FY26 and 79% in Q4 FY26” — Press release — Q1FY27 (15 Jul 2026)
Evidence (14 Oct 2026): “89% cell utilisation demonstrates strong ramp” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (21 Oct 2026): “achieving 89% effective capacity utilization during the quarter.” — Concall transcript — Q2FY27 (21 Oct 2026)
Assumptions made in reading this
- 'near term' read as the next four quarters
How this guidance changed
Stated once in the documents read so far.
Working capital days (inventory and receivables)
Hint
Working capital days are expected to normalise over coming quarters as no new capacity is added.
Targetto come down
Dueby Q4FY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusPending
In management's words
“the number of days calculation should start seeing normalized as we don’t have any further new expansion coming up in the coming quarters.”
Condition attached by management: No further new expansion coming up
Assumptions made in reading this
- 'near term' read as the next four quarters
How this guidance changed
Stated once in the documents read so far.
Inventory level
Hint
Inventory will be held at the current level or reduced by using existing stock until the new expansion comes up.
Targetto hold or improve
DueFY27
result by 30 May 2027
Said29 Apr 2026
Concall transcript
StatusPending
In management's words
“we will be mostly either maintaining the same level of inventory with the current level operation till the new expansion coming up or possibly some improvement in inventory level”
Condition attached by management: Till the new expansion comes up
Assumptions made in reading this
- no time frame was stated; checked on FY27, the year ahead at the time
How this guidance changed
Stated once in the documents read so far.
Volume growth through the year
Hint
Spare module capacity is expected to support volume growth through FY27.
Targetto improve
DueFY27
result by 30 May 2027
Said15 Jul 2026
Press release
StatusPending
In management's words
“Effective module capacity utilisation stood at 45%, providing ample headroom to support volume growth through the year.”
How it was checked
Volume is not in the stored financial tables.
How this guidance changed
Stated once in the documents read so far.
Cell line commissioning
Indirect
The Devanahalli cell line is expected to be commissioned by the end of FY 2026-27.
Targetmilestone
Dueby Q4FY27
result by 30 May 2027
Said2 Sep 2026
Annual report
StatusOn track
In management's words
“We expect the module line to be commissioned by the end of calendar year 2026, followed by the cell line by the end of FY 2026-27.”
How it was checked
The deadline of 2027-03-31 has not passed, and management says progress on the 6 GW integrated cell and module expansion is in line with plan. No commissioning date is confirmed. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
How this guidance changed
Stated once in the documents read so far.
Share of Devanahalli capex to be deployed by March 2027
Direct
About 75–80% of the Devanahalli capex is expected to be deployed by March 2027, with the balance in FY 2027-28.
Target75–80%
Dueby Mar 2027
result by 30 May 2027
Said2 Sep 2026
Annual report
StatusPending
In management's words
“Approximately 75–80% of the capital expenditure is expected to be deployed by March 2027, with the balance scheduled for FY 2027-28 in accordance with retention payment timelines.”
How it was checked
Capital expenditure as a ratio is not in the stored financial tables.
Condition attached by management: Retention payment timelines
How this guidance changed
Stated once in the documents read so far.
Demand tailwind from ALMM List II
Hint
Management expects the ALMM List II framework to boost demand over the coming quarters and support its move to a fully DCR-compliant portfolio.
Targetto improve
Dueby Q1FY28
result by 14 Aug 2027
Said15 Jul 2026
Press release
StatusPending
In management's words
“The Company expects this framework to be a demand tailwind over the coming quarters and to support its transition towards a fully DCR-compliant product portfolio.”
How it was checked
Other is not in the stored financial tables.
Condition attached by management: Depends on ALMM List II implementation from June 2026.
Assumptions made in reading this
- 'near term' read as the next four quarters
How this guidance changed
Stated once in the documents read so far.
Capacity targeted (modules)
Direct
Module capacity is targeted to rise from 10.3 GW to 16.3 GW by H1 FY28.
Target16.3 GW
DueH1FY28
result by 14 Nov 2027
Said2 Sep 2026
Annual report
StatusOn track
In management's words
“Capacity is targeted to increase from 10.3 GW modules and 2.94 GW cells to 16.3 GW modules and 8.94 GW cells by H1 FY28.”
How it was checked
The H1 FY28 deadline has not passed, and management says the 6 GW expansion progress is in line with plan. No interim module capacity figure is reported. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
How this guidance changed
Stated once in the documents read so far.
Order book delivery · Solar modules
Direct
Of the total order book, 6.3 GW is to be delivered over the next 12-18 months.
Target6.3 GW
DueFY27–FY28
result by 30 May 2028
Said15 Jan 2026
Concall presentation
StatusPending
In management's words
“Out of the Total Order Book, 6.3 GW to be delivered over the next 12-18 months”
How it was checked
Order book is not in the stored financial tables.
Assumptions made in reading this
- horizon counted from FY26 (statement made in its last quarter)
How this guidance changed
Stated once in the documents read so far.
Module capacity · Solar PV modules
Direct
Module capacity is expected to reach 16.3 GW by FY28 after the ongoing 6 GW expansion.
Target16.3 GW
DueFY28
result by 30 May 2028
Said15 Jan 2026
Concall presentation
StatusOn track
So far: Installed module capacity of 10.3 GW as of Q1 FY27 against a 16.3 GW target
In management's words
“16.3 GW by FY28”
How it was checked
The FY28 deadline has not passed, and the expansion is reported on plan, with module capacity at 10.3 GW against the 16.3 GW target. (judged from later company statements)
Evidence (15 Jul 2026): “As at the end of Q1 FY27, the Company had installed annual manufacturing capacity of approximately 10.3 GW for solar modules and 2.94 GW for TOPCon solar cells.” — Press release — Q1FY27 (15 Jul 2026)
Evidence (15 Jul 2026): “our on-track 6 GW integrated expansion give us confidence as we enter the next phase of India’s solar manufacturing growth.” — Press release — Q1FY27 (15 Jul 2026)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Condition attached by management: Depends on the ongoing 6 GW integrated facility at Devanahalli reaching commercial operation; slide 13 gives H1 FY28 for post-expansion capacity.
How this guidance changed
Stated once in the documents read so far.
Module order book executable · modules
Direct
Management plans to book only module orders it can execute within 12 to 18 months, currently about 6.3 GW.
Target~6.3 GW
DueFY27–FY28
result by 30 May 2028
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“that kind of a size of order that is 6.3 gigawatt of order that I can execute in the next 12 to 18 months is quite strong”
How it was checked
Order book is not in the stored financial tables.
Condition attached by management: Orders are taken only when backed by advance and confirmed by developer PPA and land.
Assumptions made in reading this
- horizon counted from FY26 (statement made in its last quarter)
How this guidance changed
Stated once in the documents read so far.
Total capacity (modules)
Direct
Devanahalli 6 GW facility will take total module capacity to 16.3 GW by FY2028.
Target16.3 GW
Dueby FY28
result by 30 May 2028
Said2 Sep 2026
Annual report
StatusOn track
So far: 10.3 GW module capacity in FY26
In management's words
“We are developing a 6 GW integrated cell and module manufacturing facility at Devanahalli, Bengaluru, which will take our total capacity to 16.3 GW of modules and 8.94 GW of cells by FY2028.”
How it was checked
Management reports the 6 GW expansion in line with plan. Module capacity is currently 10.3 GW, short of the 16.3 GW target, and the FY28 deadline has not passed. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Evidence (2 Sep 2026): “We commissioned two 2.5 GW solar module manufacturing lines at Sulibele, taking total module installed capacity to 10.3 GW” — Annual report FY26
How this guidance changed
Stated once in the documents read so far.
Effective cell capacity utilisation · cells
Indirect
If the market moves to G12R by 2028, cell capacity utilisation of 85% to 90% can be achieved as name-plate and effective capacity converge.
Target85–90%
Dueby 2028
result by 14 Feb 2029
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“in case by 2028 if the market decides to move in the direction of G12R that time there will be no difference between name plate and effective capacity. That time it will be full 85% utilization to 90% utilization can be achieved of the capacity.”
How it was checked
Capacity utilisation is not in the stored financial tables.
Condition attached by management: Market must move to G12R by 2028.
Assumptions made in reading this
- '2028' read as calendar year 2028
How this guidance changed
Stated once in the documents read so far.
First ingot and wafer facility · ingot-wafer
Hint
First ingot and wafer facility is planned for FY29.
Targetmilestone
DueFY29
result by 30 May 2029
Said29 Apr 2026
Concall transcript
StatusOn track
In management's words
“And we plan to set up our first facility in FY29.”
How it was checked
The Q2FY27 update says the first phase is expected to commence in FY2028-29, consistent with the FY29 plan, though it is still under evaluation. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
How this guidance changed
Stated once in the documents read so far.
Ingot and wafer Phase 1 expansion · ingot-wafer
Direct
Ingot and wafer Phase 1 is planned at 5 GW, with the first facility in FY29.
Target5 GW
DueFY29
result by 30 May 2029
Said29 Apr 2026
Concall transcript
StatusPending
In management's words
“So, with the expansion, we’re looking at a 5 gigawatt expansion in Phase 1 and a 4 gigawatt expansion in Phase 2, which is going to be a year after.”
How it was checked
Capacity is not in the stored financial tables.
How this guidance changed
Stated once in the documents read so far.
Ingot and wafer capacity · ingot and wafer
Direct
Approximately 9 GW of ingot and wafer capacity is under evaluation, with the first phase expected to start in FY 2028-29.
Target~9 GW
DueFY29
result by 30 May 2029
Said2 Sep 2026
Annual report
StatusOn track
In management's words
“we are evaluating the phased development of approximately 9 GW of ingot and wafer manufacturing capacity, with the first phase expected to commence in FY 2028-29.”
How it was checked
The Q2FY27 update still evaluates about 9 GW with the first phase expected in FY2028-29, consistent with the FY29 timing. (judged from later company statements)
Evidence (14 Oct 2026): “Progress in-line on the 6 GW integrated TOPCon cell and module expansion” — Investor presentation — Q2FY27 (14 Oct 2026)
Condition attached by management: Subject to ongoing evaluation
How this guidance changed
Stated once in the documents read so far.
Estimated investment per GW for ingot and wafer · ingot and wafer
Direct
Ingot and wafer manufacturing is estimated at INR 60,000–70,000 Lakhs per GW from FY 2028-29 onwards, under evaluation.
Target₹600 Cr – ₹700 Cr
DueFY29
result by 30 May 2029
Said2 Sep 2026
Annual report
StatusPending
In management's words
“we continue to evaluate the phased development of ingot and wafer manufacturing, with an estimated investment of INR 60,000–70,000 Lakhs per GW from FY 2028-29 onwards.”
What it implies in numbers
Reaching ₹600 Cr by FY29 from ₹881 Cr (FY26) needs about 12.0% decline a year.
How it was checked
Segment-level guidance cannot be read from company-level numbers.
Condition attached by management: Under evaluation
How this guidance changed
Stated once in the documents read so far.
Phase I upstream capacity · ingot and wafer
Direct
Phase I of upstream ingot and wafer capacity is planned at 5 GW by FY29.
Target5 GW
Dueby FY29
result by 30 May 2029
Said2 Sep 2026
Annual report
StatusPending
In management's words
“5 GW Phase I by FY29”
How it was checked
Capacity is not in the stored financial tables.
How this guidance changed
Stated once in the documents read so far.
Non-DCR module and cell demand
Hint
Management expects virtually no non-DCR demand by FY2030, with at most an immaterial amount remaining.
Targetto come down
DueFY30
result by 30 May 2030
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“by FY 2030 I don't see any capacity that is going to be of non DCR.”
How it was checked
Other is not in the stored financial tables.
How this guidance changed
Stated once in the documents read so far.
Phase II upstream capacity · ingot and wafer
Direct
Phase II of upstream ingot and wafer capacity is planned at 4 GW by FY30.
Target4 GW
Dueby FY30
result by 30 May 2030
Said2 Sep 2026
Annual report
StatusPending
In management's words
“4 GW Phase II by FY30”
How it was checked
Capacity is not in the stored financial tables.
How this guidance changed
Stated once in the documents read so far.
4.5 GW cell order · cells
Indirect
The 4.5 GW cell order is expected to be executed over 5 years.
Target~4.5 GW
Dueby FY31
result by 30 May 2031
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“Even if you see this 4.5 GW of cell is spread over 5 years.”
How it was checked
Order book is not in the stored financial tables.
Assumptions made in reading this
- horizon counted from FY26 (statement made in its last quarter)
How this guidance changed
Stated once in the documents read so far.
Reduction in interest outgo
Direct
Interest outgo is expected to fall by about Rs 35-40 crore per quarter because of the debt repaid from IPO proceeds.
Target₹35 Cr – ₹40 Cr
DueNot specified
Said2 Dec 2025
Concall transcript
StatusPending
So far: ₹155 Cr (FY26)
In management's words
“there will be reduction in the interest outgo by around 35 to 40 crores quarterly.”
How it was checked
No timeline was given; tracked against each new result.
Condition attached by management: Follows from the Rs 1,621 crore debt repayment from IPO proceeds
How this guidance changed
Stated once in the documents read so far.
Capex outlook for 6 GW integrated facility · integrated cell and module
Direct
Capex for the 6 GW integrated TopCon cell and module facility is about Rs 5,500 crore.
Target~₹5,500 Cr
DueNot specified
Said2 Dec 2025
Concall transcript
StatusPending
In management's words
“our Capex outlook for the 6 gigawatt of integrated facility of TopCon cell and module is about 5,500 crores.”
How it was checked
Segment-level guidance cannot be read from company-level numbers.
How this guidance changed
Stated once in the documents read so far.
Backward integration into wafers and ingots · wafers and ingots
Hint
Management has a plan to backward integrate into wafers and ingots, with timing still to be announced after watching ALMM developments.
Targetmilestone
DueNot specified
Said2 Dec 2025
Concall transcript
StatusPending
In management's words
“we have a plan to backward integrate into wafers and ingots. But the timeline for that is something that we would like to closely watch”
How it was checked
Milestone guidance is checked against later documents.
Condition attached by management: Timing depends on ALMM List-3 developments
How this guidance changed
Stated once in the documents read so far.
Target CoD for 6 GW integrated facility · Cells and modules (Devanahalli facility)
Hint
Management says progress on the 6 GW integrated facility is in line to achieve its target commercial operation date, which is not stated.
Targetmilestone
DueNot specified
Said15 Jan 2026
Concall presentation
StatusPending
In management's words
“Progress is in-line to achieve target CoD”
How it was checked
Milestone guidance is checked against later documents.
Condition attached by management: Design and execution planning still in progress; the target CoD date is not given in the document.
How this guidance changed
Stated once in the documents read so far.
Ingot and wafer capacity · wafers
Hint
Management intends to add ingot and wafer capacity soon but will not commit to a timeline until ALMM wafer rules and demand are clearer.
Targetmilestone
DueNot specified
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“we have also announced that we want to do ingot and wafer capacity quite soon. But the only thing is that we don't want to commit on a timeline right now.”
How it was checked
Milestone guidance is checked against later documents.
Condition attached by management: Clarity on ALMM implementation for wafers and wafer demand timing.
How this guidance changed
Stated once in the documents read so far.
Integrated cell and module facility at Devanahalli
Direct
A 6 GW integrated cell and module facility is planned at Devanahalli, with land acquired and project work on plan.
Target~6 GW
DueNot specified
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“acquired the land which is planned for 6 GW of integrated cell and module facility at Devanahalli”
How it was checked
Land is acquired and paid for, and later reports say the 6 GW Devanahalli project is progressing in line with plan and schedule. (judged from later company statements)
Evidence (29 Apr 2026): “Progress remains in line with our target commissioning schedule.” — Concall transcript — Q4FY26 (May 2026)
How this guidance changed
Stated once in the documents read so far.
ALMM-approved cell capacity · cells
Hint
Management expects ALMM-approved cell capacity to rise after a re-audit once utilisation improves, with no date given.
Targetmilestone
DueNot specified
Said16 Jan 2026
Concall transcript
StatusPending
In management's words
“once your utilization improves you can invite ALMM for an audit and they will come back and re audit it and increase the capacity accordingly.”
How it was checked
Milestone guidance is checked against later documents.
Condition attached by management: Requires utilisation to improve before audit.
How this guidance changed
Stated once in the documents read so far.
Target COD of 6 GW integrated facility
Hint
Management says the 6 GW integrated facility is progressing in line with its target commercial operation date.
Targetmilestone
DueNot specified
Said28 Apr 2026
Concall presentation
StatusPending
In management's words
“Progress is in-line to achieve target COD”
How it was checked
Milestone guidance is checked against later documents.
How this guidance changed
Stated once in the documents read so far.
Debt-equity ratio
Direct
Debt-equity will be kept within one for any further ingot-wafer funding.
Target≤ 1x
DueNot specified
Said29 Apr 2026
Concall transcript · 2× since 2 Dec 2025
StatusPending
In management's words
“even for the further ingot-wafer expansion, the whatever, you know, debt or any equity needs to be there, we are very cognizant that we’ll keep it within one the debt-equity ratio.”
How it was checked
No timeline was given; tracked against each new result.
Condition attached by management: For further ingot-wafer expansion
How this guidance changed
- 2 Dec 2025 — ≤ 1x for by Apr 2027
First stated
Concall transcript · Achieved (actual 0.1x)
- 29 Apr 2026 — ≤ 1x for Not specified
Repeated
Concall transcript · Pending
Ingot and wafer capex per GW · ingot-wafer
Direct
Ingot and wafer capex is expected at INR600-700 crore per GW.
Target₹600 Cr – ₹700 Cr
DueNot specified
Said29 Apr 2026
Concall transcript
StatusPending
In management's words
“So, yes, wafer, ingot wafer we’re looking at around INR600 crores to INR700 crores per gigawatt.”
How it was checked
Segment-level guidance cannot be read from company-level numbers.
How this guidance changed
Stated once in the documents read so far.
Capital expenditure per GW of ingot and wafer capacity · ingot and wafer
Direct
Ingot and wafer manufacturing is expected to need capex of about INR 60,000–70,000 Lakhs per GW of capacity.
Target₹600 Cr – ₹700 Cr
DueNot specified
Said2 Sep 2026
Annual report
StatusPending
In management's words
“Management has indicated that ingot and wafer manufacturing would require capital expenditure of approximately INR 60,000–70,000 Lakhs per GW of capacity.”
How it was checked
Segment-level guidance cannot be read from company-level numbers.
Condition attached by management: Project under evaluation
How this guidance changed
Stated once in the documents read so far.
Ingot and wafer capacity · ingot and wafer
Indirect
The company is evaluating a phased expansion into up to 9 GW of ingot and wafer capacity.
Target≤ 9 GW
DueNot specified
Said2 Sep 2026
Annual report
StatusPending
In management's words
“Initiated evaluation of a 9 GW ingot and wafer manufacturing programme to strengthen backward integration and supply-chain security.”
How it was checked
Capacity is not in the stored financial tables.
Condition attached by management: Subject to evaluation
How this guidance changed
Stated once in the documents read so far.
Track record · promised vs delivered
Guidance whose deadline has passed, most recent first: how management performed after giving it.
G12R cell transition from M10 · cell
Hint
Transition from M10 to G12R cells is targeted by the end of Q1 FY27, after the M10 order book runs out.
Promisedmilestonefor Q1FY27
DeliveredG12R cell manufacturing started in Q1FY27
ResultAchieved
Said29 Apr 2026Concall transcript
In management's words
“we are looking to transition in this by the end of this quarter.”
How it was checked
The Q2FY27 transcript says G12R cell manufacturing started the prior quarter, which is Q1FY27. That is within the end-Q1FY27 target. (judged from later company statements)
Evidence (21 Oct 2026): “achieving 89% effective capacity utilization during the quarter.” — Concall transcript — Q2FY27 (21 Oct 2026)
Condition attached by management: Depends on M10 order book lasting until end of May
How this guidance changed
Stated once in the documents read so far.
Long-term debt
Direct
Long-term debt, about Rs 100 crore after IPO repayment, is expected to be around Rs 50-55 crore by end of March 2026.
Promised₹50 Cr – ₹55 Crfor by Mar 2026
Delivered₹360 CrFY26
ResultMissed
Said2 Dec 2025Concall transcript
In management's words
“we'll be repaying almost 45 crores in next two quarters. So, by end of March '26, it will be around 50-55 crore long-term debt.”
What it implies in numbers
Reaching ₹55 Cr by Q4FY26 from ₹2,065 Cr (Q2FY26) needs about 99.9% decline a year.
How it was checked
FY26 actual ₹360 Cr — short of the guided ₹50 Cr – ₹55 Cr (balance sheet).
How this guidance changed
Stated once in the documents read so far.
Second 2.5 gigawatt module line · module
Indirect
The second 2.5 GW module line is expected to come online in FY2026.
Promisedmilestonefor FY26
DeliveredSecond 2.5 GW module line commissioned in December 2025
ResultAchieved
Said2 Dec 2025Concall transcript
In management's words
“The second 2.5 gigawatt module line will come online in FY 2026.”
How it was checked
Two 2.5 GW lines were commissioned at Sulibele, with the second in December 2025, within FY26 as guided. (judged from later company statements)
Evidence (29 Apr 2026): “we commissioned a 2.5 gigawatt module manufacturing line in May 2025 and another 2.5 gigawatt line in December 2025 at Sulibele, Bengaluru.” — Concall transcript — Q4FY26 (May 2026)
Evidence (29 Apr 2026): “Our installed solar module capacity increased to 10.3 gigawatt as of March 31, 2026.” — Concall transcript — Q4FY26 (May 2026)
Evidence (2 Sep 2026): “We commissioned two 2.5 GW solar module manufacturing lines at Sulibele, taking total module installed capacity to 10.3 GW” — Annual report FY26
How this guidance changed
Stated once in the documents read so far.
Key points from each document
The main takeaways, newest document first.
Concall transcript — Q2FY27 (21 Oct 2026) · 21 Oct 2026
- The 6 GW integrated cell and module expansion is about INR5,500 crore, of which about INR4,600 crore is hard cost, and module line is due December 2026 with cell line by March 2027.
- Management reiterated FY27 EBITDA guidance around INR2,400 crore and said H1 numbers make it comfortable to reach that level.
- Management reported H1FY27 revenue up 45% year-on-year to INR3,132 crore and PAT up 79% to INR762 crore, with EBITDA margin around 35%.
- Post-expansion installed capacity is expected to reach about 16.3 GW of modules and 8.9 GW of cells, with the two stages designed for broadly equivalent annual output.
- Management said domestic module demand could reach about 64% year-on-year growth this year, and that non-tendered demand is growing by 1.5 to 2 GW every month.
- Order book stood at about 10.4 GW as of 30 September 2026, with about 1.5 GW of inflows in the quarter, the highest ever in one quarter.
- Management expects margins to be maintained despite lower module prices, citing silver reduction, G12R transition and efficiency gains passed on to customers.
- Interest on the Rs 828 crore debt drawn for the expansion is being capitalised until commissioning, so finance cost stays low for now and will be recognised fully from Q1FY28.
- Management said ALMM-II deferment beyond December 2026 looks extremely unlikely, while ALMM-III is being considered for ingots and wafers.
- Backward integration into a 9 GW ingot and wafer facility is planned in two phases, with timing dependent on ALMM List-III, market conditions and economic viability.
- State capital subsidies received on the earlier project (25%) are expected on upcoming projects, but management treats them as upside and does not model them in guidance.
Investor presentation — Q2FY27 (14 Oct 2026) · 14 Oct 2026
- A 6 GW integrated TOPCon cell and module expansion is expected to take modules to about 16.3 GW and cells to about 8.9 GW by early FY28, with the module line due December 2026 and the cell line by March 2027.
- Q2FY27 revenue rose 39% YoY to Rs 15,764 mn with EBITDA margin held at 35% and PAT up 61% YoY to Rs 3,820 mn.
- Expansion capex is estimated at Rs 5,000-5,500 crore, to be funded largely through internal accruals, with about Rs 3,300 crore of debt also mentioned.
- Solar module order book stands at 10.4 GW after 1.5 GW of new order inflow in Q2FY27, giving revenue visibility.
- Plans to backward integrate into ingot and wafer with a 9 GW facility, rolled out as 5 GW in FY29 and 4 GW in FY30, depend on ALMM III timelines and market conditions.
- Management says the ALMM List-II mandate is intact from 1 June 2026 and DCR rules are unchanged, which it sees as a stable demand floor.
- Cell capacity timing is inconsistent in the deck: one slide says 8.94 GW by FY27 while another says by H1 FY28.
- Cell utilisation reached 89% while module utilisation is 44%, which management says leaves headroom for future volumes.
- Upstream supply remains a risk: wafers and ingots are about 2 GW and almost fully China-dependent, and the expansion timing depends on policy clarity.
- Finance costs fell sharply to Rs 205 mn in H1FY27 from Rs 1,084 mn in H1FY26, lifting PAT margin.
Annual report FY26 · 2 Sep 2026
- The 6 GW integrated cell and module facility at Devanahalli will take total capacity to 16.3 GW of modules and 8.94 GW of cells by FY2028.
- Management has committed INR 4,50,000–4,80,000 Lakhs to the Devanahalli facility, with about 75–80% to be deployed by March 2027.
- Management plans to expand module capacity to 16.3 GW and cell capacity to 8.94 GW by FY2028 through the 6 GW Devanahalli integrated facility.
- The company has outlined a capex programme of about INR 5,50,000 Lakhs, with hard costs of around INR 4,60,000 Lakhs for the integrated facility.
- FY26 revenue rose 116% to INR 5,04,988 Lakhs and EBITDA rose 140%, with EBITDA margin improving from 31% to 34%.
- IPO proceeds were used to prepay term loans, moving net debt-to-equity from 2.55x to negative 0.06x and lowering finance costs.
- The order book rose from 4.9 GW to 9.4 GW, including a multi-year 4.5 GW TOPCon cell supply agreement extending to 2030.
- Management is evaluating about 9 GW of ingot and wafer capacity, with the first phase expected from FY 2028-29, to complete backward integration.
- Management is evaluating up to 9 GW of ingot and wafer capacity to improve supply-chain resilience and value capture, at an estimated capex of INR 60,000–70,000 Lakhs per GW.
- Order book rose from about 4.9 GW to 9.4 GW, including a 4.5 GW long-term TOPCon cell supply agreement, giving medium-term revenue visibility.
- IPO proceeds were used to prepay INR 1,62,129 Lakhs of borrowings, and the company moved to a net cash position.
- Consolidated EBITDA margin improved to 34.34% in FY2026 from 30.91%, with PAT growing 193%.
- Revenue more than doubled to INR 5,04,988 Lakhs, driven by capacity expansion and higher production volumes.
- Auditors flagged significant FY26 additions to PPE and CWIP for solar module and cell plants at a subsidiary, a key audit matter because of capitalisation judgement.
Press release — Q1FY27 (15 Jul 2026) · 15 Jul 2026
- Revenue from operations rose 51% year-on-year to ₹1,555.5 crore in Q1 FY27, with EBITDA up 56% to ₹548.1 crore.
- EBITDA margin reached an all-time high of 35.2% and PAT margin a record 24.2%, with PAT more than doubling year-on-year.
- Order book reached an all-time high of about 9.9 GW after order inflows of 1.48 GW in the quarter, which management says gives strong revenue visibility.
- The 6 GW integrated TOPCon expansion is on track: module line by December 2026, cell line by March 2027, and about 16.3 GW of modules and 8.9 GW of cells by early FY28.
- Effective cell capacity utilisation rose to a record 83%, which management identifies as the primary driver of margin expansion through higher internal cell consumption.
- Management expects ALMM List II, which mandates domestically manufactured cells for covered projects, to be a demand tailwind over the coming quarters.
- Module capacity utilisation is only 45%, which management says leaves ample headroom to support volume growth through the year.
- The company is evaluating backward integration into ingot and wafer manufacturing through a proposed 9 GW facility in two phases; this is not yet a firm commitment.
Concall transcript — Q4FY26 (May 2026) · 29 Apr 2026
- The 6 GW integrated cell and module facility is under construction, with the module line due by end of calendar 2026 and the cell line at end of FY27.
- Management expects total installed capacity of 16.3 GW for modules and 8.9 GW for cells by end of FY27, once the 6 GW expansion is complete.
- Backward integration into ingot and wafer is planned, with about 9 GW in phases and a first facility in FY29.
- Ingot and wafer capex is guided at INR600-700 crore per GW, implying a sizeable further funding need alongside the 6 GW expansion.
- Management expects margins going into FY27 to be similar to FY26, with new orders priced on a similar profile.
- Working capital is expected to normalise as no further capacity is added, though inventory was built to support the higher run-rate.
- Management says it will keep debt-equity within one for any future ingot-wafer funding, after reporting net debt to equity of -0.06x.
- The INR3,306 crore IREDA loan at 7.95% is expected to be 75-80% drawn by 31 March 2027, with the rest spilling into FY28.
- The DCR share of sales is expected to approach nearly all capacity sold by early 2027, as ALMM rules tighten.
- Management frames FY27 as a year of execution, with focus on ramping utilisation and delivering the 6 GW expansion as planned.
Concall presentation — Q4FY26 (May 2026) · 28 Apr 2026
- The company plans a new 6 GW integrated cell and module facility, targeting total installed capacity of 16.3 GW for modules and 8.9 GW for cells by FY28.
- The order book rose from 4.9 GW to 9.4 GW during FY26, including a 4.5 GW cell order with execution running from December 2025 to 2030.
- TOPCon cell capacity is expected to reach 8.94 GW by H1 FY28 after the expansion, a slightly different timeline from the FY28 target stated elsewhere.
- Management expects the PAT margin expansion to be sustained, supported by stronger EBITDA and lower finance costs.
- FY26 revenue rose to Rs 50,499 mn, driven by higher production, first full year of cell operations and added module capacity.
- Management says progress on the 6 GW Devanahalli facility is in line with the target commercial operation date, and land is in the company's possession.
- IPO proceeds of about Rs 1,621 crore were used to prepay term loans, and IREDA has sanctioned a Rs 3,306 crore term loan for the new facility.
- Net debt to equity was (0.06)x at March 2026 and credit ratings were upgraded twice, reflecting a stronger balance sheet.
- Demand is expected to be supported by domestic content requirement schemes, and management says the company is positioned to benefit.
Concall transcript — Q3FY26 (Jan 2026) · 16 Jan 2026
- Management says EBITDA per watt peak is not under pressure for DCR or non-DCR and expects it to hold, citing pass-through contracts for raw material cost changes.
- Order book stood at 9.3 GW at 31 December 2025, including a 4.5 GW multi-year TopCon cell order, which management says gives visibility as capacity ramps up.
- Silver paste consumption per cell has been cut sharply through process R&D, and management sees room for a further reduction of about 40% from current levels.
- Management expects no non-DCR capacity demand by FY2030, with the market becoming fully DCR-linked, and sees a very small role for standalone cell sales.
- Lower blended realisation is attributed to the DCR/non-DCR sales mix rather than pricing pressure in the market.
- Installed capacity is 10.3 GW for modules and about 2.94 GW for cells, but Q3 utilisation was about 43% for modules and 76% for cells, with effective cell capacity at 2.155 GW.
- Utility-scale DCR demand is expected in about 9 to 12 months, while C&I DCR demand has already started and is described as strong.
- Approved ALMM cell capacity is about 1.6 GW against about 2.155 GW effective capacity; management says approval will rise after re-audit once utilisation improves.
- Ingot and wafer capacity is planned, but management will not commit to a timeline until ALMM wafer rules and wafer demand are clearer.
- Most new cell capacity is for captive module use, with third-party cell sales kept limited.
Concall presentation — Q3FY26 (Jan 2026) · 15 Jan 2026
- Management targets 16.3 GW of module capacity and 8.94 GW of TOPCon cell capacity by FY28 through the ongoing 6 GW integrated facility at Devanahalli.
- The order book includes a 4.5 GW multi-year TOPCon cell supply order running from December 2025 to 2030, and 6.3 GW of the total order book is to be delivered over the next 12-18 months.
- Module capacity was raised to 10.3 GW after the 2.5 GW Unit VI line was commissioned on 20 Dec 2025, and management says the expansion was completed as planned.
- EBITDA margin rose to 36% in Q3FY26 from 38% a year earlier, and management attributes the margin improvement largely to captive use of self-manufactured cells.
- Revenue from operations grew 118% year on year in Q3FY26 to INR 11,523 mn, which management links to higher capacity and better utilisation.
- Progress on the 6 GW integrated cell and module facility is described as in line with the target commercial operation date, with land fully paid and IREDA sanctioning a INR 33,060 mn term loan.
- The company is pursuing backward integration into cells and ancillary components to lower cost and secure supply, and it is positioned for India's domestic content requirement demand.
- The balance sheet is strong, with net debt to equity of (0.02)x as of 31 Dec 2025.
- Cell capacity timelines are shown as both FY28 and H1 FY28 in different slides, so the exact timing of the 8.94 GW cell target is not consistent across the document.
Concall transcript — Q2FY26 (Dec 2025) · 2 Dec 2025
- The 6 GW integrated cell and module facility at ITIR Phase 2 is expected to be fully ramped up by end of March 2027, with a capex outlook of about Rs 5,500 crore.
- Management aims to keep EBITDA margins broadly around the current band of about 35% as volumes ramp up, while investing in technology and backward integration.
- The TopCon cell line utilisation was 59% in Q2 and management expects it to rise to 85-90% by year-end, which would be a major driver of volume growth.
- After repaying Rs 1,621 crore from IPO proceeds, long-term debt is about Rs 100 crore and is expected to fall to about Rs 50-55 crore by March 2026.
- The confirmed order book is over 5 GW, giving visibility for 12-18 months, with about 20% of it being DCR orders.
- Management argues the industry's overcapacity is overstated, citing about 26 GW of Indian-made module use against 82 GW of installed capacity.
- Management says EBITDA is stable despite price changes, because most contracts are variable-price pass-through deals, but it did not clearly address whether non-DCR prices are softening.
- Lower interest outgo from the debt repayment is expected to save about Rs 35-40 crore per quarter.
- Top 10 customers account for about 80-95% of revenue, which concentrates counterparty exposure.
- Management has a plan to backward integrate into wafers and ingots, but the timing will depend on the ALMM List-3 roadmap and is not yet fixed.
- Management aims to keep debt-to-equity below one during the expansion and may fund part of the capacity build from internal accruals.
Documents read
- Concall transcript — Q2FY27 (21 Oct 2026) · Concall transcript · 21 Oct 2026 · 14 statements
- Investor presentation — Q2FY27 (14 Oct 2026) · Investor presentation · 14 Oct 2026 · 12 statements
- Annual report FY26 · Annual report · 2 Sep 2026 · 20 statements
- Press release — Q1FY27 (15 Jul 2026) · Press release · 15 Jul 2026 · 7 statements
- Concall transcript — Q4FY26 (May 2026) · Concall transcript · 29 Apr 2026 · 15 statements
- Concall presentation — Q4FY26 (May 2026) · Concall presentation · 28 Apr 2026 · 6 statements
- Concall transcript — Q3FY26 (Jan 2026) · Concall transcript · 16 Jan 2026 · 14 statements
- Concall presentation — Q3FY26 (Jan 2026) · Concall presentation · 15 Jan 2026 · 4 statements
- Concall transcript — Q2FY26 (Dec 2025) · Concall transcript · 2 Dec 2025 · 9 statements